An important milestone in EcoPro's global expansion is the opening of its first European factory in the Déli Industrial Park in Debrecen. Here, high nickel cathode materials for lithium-ion batteries are produced.

Our Substations business unit has been involved in the implementation of the following 132/22 kV substation to provide electricity supply to the facility:

  • installation of grounding grid
  • installation of outdoor GIS equipment and transformers, assembly under supervision
  • assembly and installation of relay cabinets
  • installation of fence earthing
  • busbar installation on the 20 kV side of 2 transformers and connection to the RIC busbar
  • Installation of 2 dry-type resistors and connection to the secondary system
  • secondary system installation,
  • cabling
  • installation

 

Electrical Engineering Services

On behalf of YI Engineering Ltd., we carried out the following electrical detailed design works and related engineering services:

  • preparation of primary design documentation,
  • preparation of secondary detailed design and as-built documentation.